In project management, keeping projects on track in terms of cost and schedule is crucial. Two essential performance metrics used to evaluate project efficiency are the Cost Performance Index (CPI) and the Schedule Performance Index (SPI). These indices help project managers determine whether a project is running efficiently in terms of budget and timeline.
This blog will explore what is cost performance index, its significance, how to calculate cost performance index, and the relationship between CPI and SPI. We will also go through cost performance index calculations, examples, and best practices for applying CPI in project management.

What is Cost Performance Index (CPI)?
The Cost Performance Index (CPI) is a measure of cost efficiency in a project. It evaluates how well a project is performing against its budget by comparing the earned value (EV) of work completed to the actual cost (AC) incurred. CPI is an essential metric in CPI project management, as it helps project managers determine whether they are over or under budget.
CPI Formula:
CPI=EVACCPI = \frac{EV}{AC}CPI=ACEV
Where:
EV (Earned Value): The budgeted cost of the work actually performed.
AC (Actual Cost): The total cost incurred for the work completed.
A CPI value of:
CPI > 1 → Indicates cost efficiency (under budget).
CPI = 1 → Indicates the project is on budget.
CPI < 1 → Indicates cost overrun (over budget).
Cost Index Meaning in Project Management
The cost performance index formula helps in understanding whether a project is being executed cost-effectively. If a project has a CPI value below 1, it means that more money is being spent than planned for the work done. Conversely, a CPI above 1 indicates cost savings and efficiency.
How to Calculate Cost Performance Index
Understanding how to calculate CPI is essential for project managers to maintain control over project costs. Let’s go through the process step by step.
Step 1: Determine Earned Value (EV)
The earned value (EV) is the budgeted amount for the work that has been completed up to a specific point in the project.
EV=Percentage of work completed×Budget at Completion (BAC)EV = \text{Percentage of work completed} \times \text{Budget at Completion (BAC)}EV=Percentage of work completed×Budget at Completion (BAC)
Step 2: Determine Actual Cost (AC)
The actual cost (AC) is the total amount spent on the completed work at a given point in time. This includes all labor, materials, and indirect costs incurred.
Step 3: Apply the CPI Equation
Once you have EV and AC, apply the CPI formula:
CPI=EVACCPI = \frac{EV}{AC}CPI=ACEV
Cost Performance Index Example
Let’s say a project has:
Budget at Completion (BAC) = $100,000
Work completed = 50%
Actual cost incurred = $60,000
First, calculate EV:
EV=50%×100,000=50,000EV = 50\% \times 100,000 = 50,000EV=50%×100,000=50,000
Now, apply the CPI equation:
CPI=50,00060,000=0.83CPI = \frac{50,000}{60,000} = 0.83CPI=60,00050,000=0.83
Since CPI < 1, this means the project is over budget.
What is Schedule Performance Index (SPI)?
While CPI focuses on cost efficiency, the Schedule Performance Index (SPI) measures the efficiency of schedule performance. What is schedule performance index? It is calculated as follows:
SPI=EVPVSPI = \frac{EV}{PV}SPI=PVEV
Where:
PV (Planned Value): The estimated cost of planned work up to a specific time.
EV (Earned Value): The actual value of work completed.
An SPI value of:
SPI > 1 → Ahead of schedule.
SPI = 1 → On schedule.
SPI < 1 → Behind schedule.
CPI vs SPI – Understanding the Differences
Both CPI and SPI are used in project management, but they measure different aspects:
Metric | Formula | Interpretation |
CPI (Cost Performance Index) | CPI = EV / AC | Measures cost efficiency |
SPI (Schedule Performance Index) | SPI = EV / PV | Measures schedule efficiency |
CPI and SPI Together
A high CPI and low SPI indicate cost efficiency but schedule delays.
A low CPI and high SPI indicate budget overruns but timely progress.
A CPI and SPI both below 1 indicate a project facing budget and schedule issues.
Importance of CPI in Project Management
The CPI project management metric is crucial for:
Cost Control – Helps in identifying cost overruns early.
Decision-Making – Assists managers in reallocating resources efficiently.
Budget Forecasting – Predicts the final cost of the project.
Performance Evaluation – Determines project efficiency.
Cost Performance Index and Schedule Performance Index Together
Both CPI and SPI are essential for effective project management. They provide insights into whether a project is progressing as planned in terms of budget and time.
How to Improve Cost Performance Index
If your CPI is below 1, indicating cost overruns, consider these strategies:
Identify Cost Overruns Early
Monitor cost performance index calculations frequently.
Optimize Resource Allocation
Adjust labor and material usage to stay within budget.
Reduce Unnecessary Costs
Cut non-essential expenses that do not impact project deliverables.
Improve Project Planning
Enhance forecasting methods to prevent miscalculations.
Use CPI and SPI Together
Balancing cost and schedule performance ensures overall project success.
Conclusion
Understanding what is cost performance index and how to calculate cost performance index is essential for project managers. CPI helps in assessing the financial health of a project, while schedule performance index (SPI) ensures projects stay on track in terms of timeline.
By monitoring CPI and SPI, managers can proactively address budget and schedule issues, ensuring successful project completion.
To summarize:
CPI > 1 → Project is under budget.
CPI = 1 → Project is on budget.
CPI < 1 → Project is over budget.
SPI > 1 → Ahead of schedule.
SPI = 1 → On schedule.
SPI < 1 → Behind schedule.
By consistently monitoring and applying cost performance index calculations, project managers can maintain control over project budgets, schedules, and overall efficiency.
Subscribe and share your thoughts and experiences in the comments!